Port Authority of NY & NJ
JFK International Airport
Administration Building 14
Jamaica, NY 11430
Project
Essential FADRS® Demonstration Pilot
Smart Grid Technology Showcase utilizing FADRS® patented Artificial Intelligence, Prediction & Human Centric Technology.
Contractors
Consolidated Energy Design (Patent Holders)
Third Party BAS Contractor (Installation)
Funding Agency
New York Power Authority
Pre-Conditions
Locker Room Area of JFK Facility Administration Building 14
45,000 square feet of the 750,000-square-foot building
HVAC Air Handling Unit AC-7 and Exhaust Fan EF-7
Siemens Building Automation System (BAS) for space heating/cooling.
Post Conditions
- New control sensors and relays
- New VFD for each unit (total 2)
- New Distech Tridium Controllers
- FADRS® Enhanced Building Automation System
FULLY AUTOMATED, Bidirectional control in near or real-time. No Human Intervention and self-healing.
System Start Date: March 15, 2023
Normalized Baseline (NBL) for HVAC – AC-7 = 101,202 kWh ($15,180)
HVAC Energy Savings by December 31, 2023
Savings 94,486 kWh ($14,173) = 93.4%
Normalized Baseline (NBL) for HVAC – EF-7 = 58,039 kWh ($8,706)
HVAC Energy Savings by December 31, 2023
Savings 53,532 kWh ($8,030) = 92.2%
Normalized Baseline (NBL) Combined AC-7 & EF-7 = 159,241 kWh ($23,886)
HVAC Energy Savings by December 31, 2023
Savings 148,018 kWh ($22,203) = 93.0%