Management
NAI Emory Hill Real Estate Group
7250 Parkway Drive, Hanover, MD
Project
FADRS® (pronounced faders)
Near Net Zero
Contractors
Consolidated Energy Design (Patent Holders)
Third Party BAS Contractor (Installation)
Funding Agency
C-PACE funding through Counterpointe Sustainable Real Estate and incentives from Maryland Energy Administration (MEA) and Baltimore Gas and Electric
Pre-Conditions
- 5 Story Tenant Occupied Office Building; 81,000 square feet
- 85 Water Source Heat Pumps
- Typical Building Automation System (BAS) for space heating/cooling
Post Conditions
- DEEP Lighting and Plug load Retrofits
- FADRS® Painless Demand Response®
- FADRS® Next Generation Enhanced BAS
- ~105 Power Quality Sub Meters
- Distributed Generator
- Battery Energy Storage System (BESS)
- Solar PV (minimum requirement of 72 KW)
- EV Charging Stations
ALL ECMs either overlaid on top of existing BAS or reporting to existing BAS.
FULLY AUTOMATED control (No Human Intervention). Bidirectional control in real-time.
Completion Date
FADRS® Near Net Zero Enhanced Building Automation System Performance: Enhanced Energy Savings from April 1, 2022, to March 31, 2023
Normalized Baseline (NBL) for HVAC, Plug Loads & Lighting = 1,580,909 kWh ($185,915) AI Achieved Maximum Energy Savings by March 31, 2023 823,218 kWh ($79,111) = 47%
FADRS® Painless Demand Response® Performance: (12/24/22 Winter Capacity Event) 139 KW down to 0 KW AC (This Event lasted 15 hours) = 100% DR Reduction